Skip to main content Skip to footer

Knocknair Renewable Energy Park

Introduction

Renewco Power is bringing forward a new solar energy project near Devol Moor in Inverclyde, Scotland. The project is called Knocknair Renewable Energy Park and will include up to 25MW of Solar PV panels and a 24.9MW Battery Energy Storage System (BESS).

Although the Knocknair project is still in its early stages, Renewco remains fully committed to engaging with the local community from the outset. As part of this commitment, the first consultation event will be held on 7th May 2025 at Port Glasgow Town Hall (Shore St, Port Glasgow PA14 5HD), from 3-7pm.

Location

The Knocknair site is located just south of Dougliehill Road in Inverclyde, located 1.5km South East of Greenock and 0.5km South of Port Glasgow, near Devol Moor.

Our Proposal

In December 2024, we submitted an Environmental Impact Assessment (EIA) Screening request to Inverclyde Council to help identify key environmental considerations that consultees would like addressed in any future application for Knocknair Renewable Energy Park.

Building on this, we recently submitted a Proposal of Application Notice (PoAN) to Inverclyde Council. This marked the start of the statutory 12-week pre-application consultation phase, ensuring meaningful engagement with the community and stakeholders as the project develops.

Preliminary feasibility work at Knocknair is already underway. So far, we have developed an initial layout featuring approximately 700 solar frames and a Battery Energy Storage System (BESS). As the project progresses, the design will continue to evolve, shaped by consultation feedback and detailed environmental assessments. The following documents will be submitted as part of the planning application:

  • Landscape and Visual Impact Assessment;
  • Noise Impact Assessment;
  • Archaeology & Heritage Impact Assessment;
  • Water Environment Appraisal;
  • Private Water Supply Risk Assessment;
  • Flood Risk Assessment;
  • Surface Water Management Plan;
  • Peat Technical Note;
  • Glint & Glare Assessment;
  • Ecological Impact Assessment;
  • Outline Construction Environmental Management Plan;
  • Transport Statement; and
  • Construction Traffic Management Plan.

Indicative Development Timescale

May 2025

First public consultation

June 2025

Second public consultation

Autumn 2025

Target Submission Date for Planning Approval

Why is this project needed?

The Scottish Government has set targets to reduce Scotland’s emissions of all greenhouse gases to net zero by 2045 at the latest. Significant additional renewable energy capacity, over and above what is produced today, will be needed to facilitate the decarbonisation of transport and heating as Scotland transitions to net zero. The latest National Planning Framework explicitly aims to ‘encourage, promote and facilitate all forms of renewable energy development,’ including solar arrays and battery storage.

Upcoming public engagement activities

The first public consultation for Knocknair Renewable Energy Park will take place on 7th May 2025 at Port Glasgow Town Hall (Shore St, Port Glasgow PA14 5HD) from 3-7pm.

This event will provide an opportunity for the public to learn more about the plans for the project, meet the project team, and share feedback on the Knocknair Renewable Energy Park. Input gathered during this process, will be considered as the design progresses, with changes incorporated where feasible.

Get In touch

If you would like to get in touch with us in relation to the Knocknair Renewable Energy Park, please email: Samuel.rowe@cavendishconsulting.com

Frequently Asked Questions

Solar technologies capture solar rays from the sun and turn it into useful forms of energy. Photovoltaic (PV) panels comprise several PV cells (which typically produce 1-2 watts of power each) with a whole panel typically producing 250-700 watts depending on the make and model. These PV cells are made of different semiconductor materials, such as silicone, and are sandwiched between protective materials in a combination of glass and / or plastics. When a photon of light from the sun strikes the semiconductor material, it displaces charged particles known as electrons and creates an electrical current. This Direct Current (DC) electricity is then able to be extracted via conductive metal contacts and converted to Alternating Current (AC) electricity via inverters for transmission via the electricity network.

The construction traffic will adhere to an agreed Traffic Management Plan with the council, which will include the use of an existing built access track to avoid impacting local residents. The construction period is expected to take approximately 12 months, and during this time there will be deliveries of equipment to the site. However, the construction period which generates the most traffic is only expected to last 6 months. To manage any potential impacts, Renewco Power and Wardell Armstrong have put in place measures to control construction traffic and minimise disruption to local roads

If consented, the Knocknair Renewable Energy Park project will be subject to a planning condition restricting the total length of the operational period to a maximum of 40 years. At the end of this period, the project will be required to be fully decommissioned, and the land reinstated to its pre-existing condition as agricultural land to the satisfaction of the Local Planning Authority. The details of these decommissioning activities will be secured via a Decommissioning Plan to be submitted for the Council’s approval before the end of the project’s lifespan. It is considered that grazing will continue during the operational period.

A desktop Noise Impact Assessment has been carried out and a report submitted as part of the planning application. Therefore, any operational noise from the project would be low and would comply with all proposed noise limits during all periods of the day and night.

 

The battery storage system is designed to have a very low risk of failure. However, in the unlikely event that a failure should occur, monitoring equipment including fire detection and fire prevention systems will be installed within the containerised battery units to ensure that any emergency remains under control. The site access will also be designed to ensure that fire appliances can safely access and egress the site. Renewco Power are consulting with the Fire and Rescue Service as part of the design and are continuing to monitor industry best practice to ensure that the highest standards of safety are maintained for these units.

Get in touch

We are interested in engaging with wind and solar asset owners, land-owners, developers and funders.

Cookie policy

Learn more about how we use cookies on our website to improve your experience.